Performance
Reviews - Treatment of Anodising, Etching and Plating Effluents
A manufacturing site which carried
out considerable amounts of aluminium etching and chrome anodising
together with lesser amounts of other electroplating and surface
finishing activities had developed compliance problems within
its effluent discharge. RPA carried out a thorough review
of the chrome reduction and other relevant aspects of the
treatment plant, the effluent collection arrangements and
the effluent sources themselves. This review was based upon
both the current effluent profiles and the range of likely
future profiles.
RPA identified that the current problems could be overcome
by a combination of minor plant changes and operator re-training.
The designs for these changes were developed such that both
the current and the predicted future requirements would be
overcome at the same time. The necessary capital investment
had a pay back of less than six months. RPA also carried out
the operator re-training and issued amended operating and
maintenance manuals.
The same facility also commissioned RPA to carry out a detailed
mass balance for all financially and environmentally significant
components around its component plating, pickling and rinse
water recovery line. This study highlighted rinse inefficiencies
which affected product quality and resulted in unnecessarily
high operating costs and reagent usage. Relatively simple
changes to the operating and control concepts, particularly
within the rinse water recovery equipment overcame the quality
problems and created significant savings as regards both production
costs and environmental load.
The above studies were sufficiently thorough to form the
basis for the site’s IPPC application.
Steel Mill Rolling, Surface Cleaning,
Plating and Painting Effluents
As part of the Environmental Master Plan work for a large
Iron and Steel Facility in South Africa, one of the urgent
short term measures was to overcome the operating difficulties
at the effluent treatment plant for the hazardous effluents.
The plant was complex, suffered from the effects of surges
in the flow of individual input streams (causing occasional
short duration exceedances in the output quality criteria),
and the discharge criteria were about to be tightened to a
level which were not achievable by the process routes that
were being used, even when all aspects were working ideally.
RPA looked at all the different treatment processes and realised
that they were all set up in a manner which represented the
logical ideal for that particular effluent on its own. The
processes took no account of what could be achieved by using
one effluent to assist in the treatment of another. For example,
some of the acidic effluents contained sufficient Fe2+ to
enable all of the Cr6+ to be treated without the need for
a separate pre-treatment process for all the chrome effluents.
Similarly, if all the acidic effluents were pH neutralised
together, the resultant aqueous phase contained enough dissolved
calcium to precipitate all the fluorides in the other effluent
streams, whilst keeping the final sulphate concentration within
limits.
RPA developed a way of re-arranging pipe work and controls
such that all these process improvements could be achieved
using only the existing equipment and buffer storage arrangements.
This scheme enabled almost half of the processing stages to
be shut down, over half of the previous reagent consumption
to be avoided and for the ultimate production of sludge residues
from all the treatment processes to be reduced to less than
25%. At the same time, the new quality criteria for the effluents
were able to be met and the frequency and magnitude of non-compliances
was greatly reduced.
RPA then looked at the causes of the remaining non-compliances
and together with the relevant site staff, evolved and implemented
a sequence of upgrades and changes at the different effluent
sources and transfer arrangements as well as within the remaining
treatment equipment, such that all the remaining causes of
quality exceedances were overcome.
Next : Project
Concept to Completion Case Study 1 >
|